Activity | Person Responsible | Start Date | Deadline | Status | Status Explanation | Actions |
---|---|---|---|---|---|---|
2019-09-20 | 2019-11-30 | 25% Progress | Currently liaising with provinces and districts | |||
2019-08-28 | 2019-09-30 | 0% Progress | Not yet due | |||
2019-10-01 | 2019-11-30 | 0% Progress | Not yet due | |||
2019-08-28 | 2019-09-30 | 10% Progress | Inaugural meeting for the committee was held | |||
2019-09-20 | 2019-10-04 | 20% Progress | Meetings with other committees not yet held | |||
2019-09-20 | 2019-11-30 | 0% Progress | Not yet due | |||
2019-08-28 | 2019-09-30 | 0% Progress | Not yet due | |||
2019-09-13 | 2019-09-20 | 100% Complete | The activity was completed on 20th September. | |||
2019-09-18 | 2019-10-25 | 75% Progress | The committee has begun consulting the Technical and Implementation subcommittee. | |||
2019-09-13 | 2019-11-30 | 60% Progress | Vendors are being identified | |||
2019-10-01 | 2019-11-30 | 0% Progress | Not yet due |